Question 57 of 110Numerical Abilitytime and work

A supervisor engages 32 men to lay a warehouse floor in 21 days. At the start of the work, 8 of the men are transferred to another site and never work on the floor at all. In how many days will the remaining men lay the floor, all of them working at the same standard rate?